The Misau-Bulkachuwa-Undubo road in Bauchi State is 87km. The road was in a deplorable state when we came in. 

The project involved improvement of Roads Vertical and Horizontal Alignments, Re-design of Bridges, Culverts and Upgrading of the Road Pavement to comply with current Ministry’s specifications and standards. Preliminary and final design documents including Stoical Calculations Reports, construction drawings, Bending Schedules, Quantity estimates and BOQ were produced.

DETAILED DESIGN AND SUPERVISION OF THE CONSTRUCTION KAMFANIN KUTARE – KUBI SHANGO-BALAKANAWA – GUNURA SORO ROADS (PHASE 1) (128KM)

Client Name
: Bauchi State Government Ministry of Works & Transport
Service
: Civil Engineering
Start Date
: 1st August, 2017
End Date
: 1st December, 2018
Status
: Completed